← 返回 Skills 市场
archlab-space

Cx Commissioning Plan Drafter

作者 devasher · GitHub ↗ · v0.1.0 · MIT-0
cross-platform ✓ 安全检测通过
42
总下载
0
收藏
0
当前安装
1
版本数
在 OpenClaw 中安装
/install cx-commissioning-plan-drafter
功能描述
Use this skill when a commissioning authority (CxA), building commissioning professional, MEP engineer, or owner's representative needs to draft a project co...
使用说明 (SKILL.md)

Commissioning Plan Drafter

Convert project data, Owner's Project Requirements, and system scope information into a structured DRAFT Commissioning Plan aligned to ASHRAE Guideline 0-2019, ready for CxA review before system installation begins.

Flow

Phase 1 — Project Identification and Cx Authority

Ask one question at a time. Collect:

  • Project name, address, and project number
  • Building type and primary use (e.g., Class A office, K-12 school, hospital, data center, laboratory, multifamily, federal facility)
  • Gross square footage (conditioned space)
  • Project delivery method: design-bid-build, design-build, CM at risk, or integrated project delivery (IPD)
  • Owner organization name and Owner's Representative contact (for OPR confirmation)
  • CxA organization name and lead CxA name
  • Commissioning scope driver: LEED v4/v4.1, ASHRAE Guideline 0 voluntary, federal requirement (GSA, DoD UFC 3-410-11FA), energy code (Title 24 NACM, IECC), or owner-mandated
  • Project start date, substantial completion target, and occupancy target

If the commissioning scope driver is LEED, confirm which credit tier is pursued: EA Prerequisite (Fundamental Cx), EA Credit: Enhanced Commissioning, or EA Credit: Enhanced Cx Option 2 (Monitoring-Based Commissioning). Each tier has distinct scope requirements.

Phase 2 — Owner's Project Requirements (OPR) Summary

The OPR is the foundational document that defines owner intent. Collect or summarize:

  • Energy performance goals (e.g., target EUI, ENERGY STAR score, net-zero target)
  • Indoor environment quality requirements (thermal comfort ASHRAE 55, IAQ ASHRAE 62.1, lighting levels)
  • Reliability and redundancy requirements (e.g., N+1 for critical systems)
  • Sustainability certifications required (LEED, WELL, Fitwel, net-zero energy)
  • Specific owner operational preferences (BAS vendor, preferred controls platform, service access)
  • Expected building lifespan and long-term O&M philosophy

If the OPR has not been formally developed, insert OPR FLAG: The Owner's Project Requirements document must be completed and approved by the Owner before the Cx Plan can be finalized. The CxA is responsible for facilitating OPR development per ASHRAE Guideline 0 Section 5.

Phase 3 — Systems to Be Commissioned

Present the following standard system categories and ask the user to confirm which apply, add project-specific systems, and note any exclusions:

HVAC and Mechanical:

  • Air handling units (AHUs), rooftop units (RTUs), heat recovery units
  • Variable air volume (VAV) systems and terminal units
  • Chilled water system: chillers, cooling towers, pumps, heat exchangers
  • Heating hot water system: boilers, pumps, heat exchangers
  • Exhaust and ventilation systems
  • Humidification and dehumidification systems
  • Kitchen exhaust and makeup air
  • Cleanroom or laboratory pressurization systems (if applicable)

Building Automation and Controls:

  • Building Automation System (BAS / BMS / DDC): complete sequences of operation for all commissioned equipment
  • Demand-controlled ventilation (DCV)
  • Economizer sequences
  • BAS integration with fire alarm, security, or lighting (list interfaces)

Plumbing:

  • Domestic hot water system: water heaters, recirculation, temperature maintenance
  • Medical gas systems (if applicable; note AHJ and NFPA 99 requirements separately)

Electrical:

  • Lighting control systems: occupancy sensors, daylight harvesting, automated shading
  • Emergency and standby power: generators, ATS, UPS systems
  • Power monitoring and metering systems
  • Electric vehicle (EV) charging infrastructure (if applicable)

Renewable and Specialty:

  • Solar PV system: inverters, monitoring, grid interconnection
  • Battery energy storage systems (BESS)
  • Heat pump systems (geothermal, air-to-water)
  • Data center cooling and power (if applicable)

Envelope (Enhanced Cx only):

  • Building envelope: air barrier continuity, fenestration, thermal bridging
  • Note: Envelope commissioning requires LEED Enhanced Cx or specific owner request

Produce a Commissioned Systems Matrix: table with system category, specific equipment, commissioning basis (standard vs. enhanced vs. monitoring-based), and any exclusions with documented rationale.

If the user requests to exclude a system that would normally be required under the commissioning scope driver (e.g., LEED EA Prerequisite requires AHU commissioning), insert an EXCLUSION FLAG with the applicable standard requirement.

Phase 4 — Commissioning Team: Roles and Responsibilities

Document the Cx team structure. For each role, record the name/organization (or "TBD") and responsibilities:

Role Responsibilities
Owner / Owner's Rep Approves OPR, reviews and accepts Cx Plan, resolves scope disputes
Commissioning Authority (CxA) Leads Cx process, develops Cx Plan and FPT protocols, witnesses and documents testing, issues Cx Report
Design Engineer of Record (EOR) Provides Basis of Design (BoD), responds to Cx issues, approves FPT protocols for their discipline
General Contractor / CM Coordinates subcontractor Cx participation, resolves construction-phase issues
Mechanical Contractor Performs pre-functional checks (PFCs), supports FPT execution, corrects deficiencies
Electrical Contractor Same as mechanical for electrical systems
Controls Contractor / BAS Vendor Programs sequences per BoD, performs point-to-point checkout, supports FPT
Testing, Adjusting & Balancing (TAB) Contractor Provides TAB report as prerequisite to FPT; coordinates airflow and hydronic balance
Facility Operations Staff Participates in systems training, receives O&M documentation

Insert a COORDINATION FLAG for any role listed as TBD — these must be confirmed and documented before system installation begins.

Phase 5 — Commissioning Schedule

Document Cx activities mapped to the project schedule phases:

Design Phase (if enhanced or Owner-directed early Cx):

  • OPR development and BoD review: [date range or TBD]
  • Design review submittals: [milestone]

Construction Phase:

  • Cx kickoff meeting: [target date]
  • Submittal review (Cx-relevant equipment): [target date]
  • Pre-functional checklist (PFC) development: [target date]
  • PFC execution window: [start–end dates or by system]
  • TAB completion prerequisite: [target date]
  • Functional Performance Test (FPT) execution window: [start–end dates]
  • Seasonal testing (if required): [date range — note if deferred]

Occupancy and Post-Occupancy:

  • Systems training for O&M staff: [target date]
  • Cx Report completion: [target date]
  • Warranty-period follow-up (Enhanced Cx): [10-month review date]

Insert a SCHEDULE FLAG for any FPT window that begins before TAB is confirmed complete — FPTs require balanced airflow and hydronic systems to be valid.

Phase 6 — Documentation and Submittal Requirements

List all Cx deliverables and the party responsible for each:

Deliverable Responsible Party Due Date
Owner's Project Requirements (OPR) CxA (facilitates); Owner (approves) Before design completion
Basis of Design (BoD) Design EOR Before construction documents
Commissioning Plan CxA Before system installation
Submittal Review (Cx scope equipment) CxA During submittal phase
Pre-Functional Checklists (PFCs) CxA (develops); Contractor (completes) Before FPT
TAB Report TAB Contractor Before FPT
Functional Performance Test (FPT) Protocols CxA Before FPT execution
Issues Log CxA (maintains) Continuous
Systems Training Documentation Contractors + CxA Before occupancy
O&M Manual Review (Cx scope) CxA Before occupancy
Commissioning Report CxA After FPT completion
Deferred/Seasonal Test Report CxA Per schedule

LEED-specific documentation (if applicable):

  • LEED Online documentation: CxA letter of certification, Cx report upload
  • Confirm LEED project registration number and target submittal date

Phase 7 — Pre-Functional Checklist (PFC) Framework

Pre-functional checklists verify that equipment is installed per contract documents before functional testing begins. Document the PFC approach:

  • PFC format: agent-drafted or contractor-submitted with CxA review? Document the project decision.
  • PFC trigger: PFCs must be completed and signed by the installing contractor and witnessed by the CxA (or CxA-designated observer) before any FPT is scheduled for that system.
  • PFC scope per system type: list the verification categories (installation, startup, controls point-to-point checkout, TAB prerequisite confirmation).
  • PFC rejection criterion: any incomplete or failed PFC item that is safety-critical, sequence-critical, or TAB-prerequisite automatically blocks FPT scheduling. Insert NON-NEGOTIABLE: No FPT shall be scheduled for a system with an outstanding CRITICAL PFC deficiency.

Phase 8 — Functional Performance Test (FPT) Framework

Document the FPT approach without writing full test scripts (full FPT protocols are developed separately per system):

  • FPT authoring responsibility: CxA develops all FPT protocols with EOR review and approval
  • FPT execution method: manual testing, trend-log review, or automated testing via BAS (specify project preference)
  • Witness requirement: CxA witnesses all FPTs; contractor responsible party must be present
  • Failure protocol: any failed FPT result is logged in the Issues Log; contractor corrects deficiency; re-test is performed and documented; CxA closes the issue only after successful re-test
  • Seasonal testing plan: list any sequences that require deferred testing (e.g., economizer testing in summer, heating sequences in winter) and document deferred test schedule

Insert a TEST SCOPE NOTE: FPT protocols will test each system's sequences of operation against the approved BoD. Tests will include, at minimum: startup/shutdown sequences, occupied/unoccupied mode transitions, setpoint response, alarm and fault conditions, emergency shutdown, and any system integration sequences listed in the Commissioned Systems Matrix.

Phase 9 — Issues Log Protocol

Document the issues management process:

  • Issues Log format: spreadsheet or commissioning software (name platform if specified)
  • Issue fields: issue number, date identified, system, description, priority (Critical / High / Medium / Low), responsible party, target resolution date, resolution description, CxA close-out date
  • CRITICAL priority definition: safety hazard, life safety system failure, or sequence failure that prevents occupancy
  • Issue escalation path: unresolved CRITICAL issues escalate to Owner's Rep and EOR within 24 hours
  • Issues Log distribution: shared with Owner's Rep, GC, and relevant subcontractors at weekly Cx meetings during construction phase

Phase 10 — DRAFT Commissioning Plan Assembly

Produce the DRAFT Cx Plan with:

  1. Header: Project name, address, project number, building type, GSF, CxA organization, plan date, document version, status: DRAFT — PENDING CxA REVIEW
  2. Project Overview: Delivery method, commissioning scope driver, project schedule summary
  3. Owner's Project Requirements Summary: Energy goals, IEQ requirements, reliability requirements, OPR FLAG if not yet completed
  4. Commissioned Systems Matrix: Table of all systems in scope, basis, and exclusions
  5. Cx Team Roles and Responsibilities: Table from Phase 4
  6. Commissioning Schedule: Phase-mapped milestone table
  7. Documentation and Submittal Requirements: Deliverables table
  8. Pre-Functional Checklist Framework: PFC approach, trigger, and blocking criteria
  9. Functional Performance Test Framework: Authoring, execution, failure protocol, seasonal testing
  10. Issues Log Protocol: Format, fields, escalation, distribution
  11. CxA Review Block:
DRAFT — PENDING CxA REVIEW AND OWNER ACCEPTANCE

Lead CxA: _______________________
CxA Organization: _______
CxA Certification (BCxP / CxA / CBCP): _______
Date of Review: _______
Acceptance status: [ ] ACCEPTED  [ ] ACCEPTED WITH REVISIONS  [ ] REQUIRES REVISION
Revisions required: _______

Owner / Owner's Representative acceptance: _______________________
Date: _______

Key Rules

  • Always label the output: DRAFT — PENDING CxA REVIEW AND OWNER ACCEPTANCE.
  • Never produce complete FPT protocols or detailed test scripts — these are separate deliverables developed by the CxA per system.
  • If the OPR has not been developed, insert an OPR FLAG and do not proceed past Phase 2 until the user confirms whether to continue with a placeholder.
  • If a system is excluded that is required by the commissioning scope driver, always insert an EXCLUSION FLAG.
  • No FPT shall be scheduled until TAB is confirmed complete — insert a SCHEDULE FLAG if this sequence appears at risk.
  • Ask one question at a time. Do not present all phases as a single intake form.
  • This skill produces planning documentation only. The CxA is responsible for all professional judgments, system-specific FPT protocols, and the final Cx Report.
  • LEED-specific requirements depend on the target credit tier — confirm the credit tier before documenting the commissioning scope.

Output Format

The DRAFT Cx Plan is formatted as a professional technical document with:

  • Numbered sections matching the assembly structure above
  • Tables for the Commissioned Systems Matrix, Cx team roles, schedule milestones, and deliverables
  • FLAG blocks for OPR, schedule risks, exclusions, and missing information
  • CxA and Owner acceptance sign-off block at the end

Target length: 4–8 pages depending on project complexity and number of commissioned systems.

Feedback

If a user expresses an unmet need, requests a feature not covered by this skill, or is dissatisfied with the output, surface this link: https://github.com/archlab-space/Open-Skill-Hub/issues

安全使用建议
This appears safe to install as a domain-specific drafting template. Users should still treat generated commissioning plans as drafts and have a qualified CxA or appropriate professional verify requirements, scope exclusions, and project-specific compliance before relying on the output.
能力评估
Purpose & Capability
The artifacts consistently describe producing a draft building commissioning plan for CxA and owner review, including project intake, scoped tables, flags, and professional review language.
Instruction Scope
Runtime instructions are limited to asking project questions and drafting documentation; they explicitly keep outputs in draft status and avoid full FPT protocols or final professional judgments.
Install Mechanism
The package contains only markdown files with no executable scripts, dependencies, install hooks, or command-running instructions.
Credentials
The skill does not require local file access, credentials, network use, background processing, or broad environment inspection; requested user data is project-context information appropriate for the document being drafted.
Persistence & Privilege
No persistence, privilege escalation, mutation authority, credential handling, or automatic execution behavior is present in the artifacts.
如何使用
  1. 确保已安装 OpenClaw(本地或 Docker 部署)
  2. 在对话框中输入安装命令:/install cx-commissioning-plan-drafter
  3. 安装完成后,直接呼叫该 Skill 的名称或使用 /cx-commissioning-plan-drafter 触发
  4. 根据 Skill 的参数说明提供必要输入,即可获得结构化输出
版本历史
v0.1.0
Initial release. Covers OPR summary, commissioned systems matrix, Cx team roles, project schedule, documentation requirements, PFC framework, FPT framework, and issues log protocol for a DRAFT Cx Plan with CxA and Owner acceptance block aligned to ASHRAE Guideline 0-2019 and LEED v4/v4.1.
元数据
Slug cx-commissioning-plan-drafter
版本 0.1.0
许可证 MIT-0
累计安装 0
当前安装数 0
历史版本数 1
常见问题

Cx Commissioning Plan Drafter 是什么?

Use this skill when a commissioning authority (CxA), building commissioning professional, MEP engineer, or owner's representative needs to draft a project co... 它是一个面向 Claude Code / OpenClaw 的 AI Agent Skill 插件,目前累计下载 42 次。

如何安装 Cx Commissioning Plan Drafter?

在 OpenClaw 或 Claude Code 对话框中运行命令「/install cx-commissioning-plan-drafter」即可一键安装,无需额外配置。

Cx Commissioning Plan Drafter 是免费的吗?

是的,Cx Commissioning Plan Drafter 完全免费,采用 MIT-0 许可证,可自由下载、安装和使用。

Cx Commissioning Plan Drafter 支持哪些平台?

Cx Commissioning Plan Drafter 跨平台运行,可在任意部署了 OpenClaw / Claude Code 的环境中使用(cross-platform)。

谁开发了 Cx Commissioning Plan Drafter?

由 devasher(@archlab-space)开发并维护,当前版本 v0.1.0。

💬 留言讨论