← Back to Skills Marketplace
lnj22

fjsp-baseline-repair-with-downtime-and-policy

by lnj22 · GitHub ↗ · v0.1.0 · MIT-0
cross-platform ✓ Security Clean
71
Downloads
0
Stars
0
Active Installs
1
Versions
Install in OpenClaw
/install manufacturing-fjsp-optimization-fjsp-baseline-repair-with-downtime-and-policy
Description
This skill should be considered when you need to repair an infeasible or non-optimal flexible job scheduling planning schedule into a downtime-feasible, prec...
README (SKILL.md)

This skill should be considered when you need to enhance a given infeasible or non-optimal fjsp baseline to a feasible schedule with less makespan considering downtime constraints, job precedence violations, policy budget constraints. The following constraints should be satisfied. end(j, o) \x3C= start(j, o+1). Here j means the job index and o means the operation index. There should be no overlaps on the same machine or with downtime windows. Keep the number of machine changes and the total L1 start-time shift within the policy budgets. You can calculate the number of machine changes by MC = \sum_{(j,o)} [m_{new}(j,o)
e m_{base}(j,o)]. You can calculate the total L1 start-time shift by Shift_{L1} = \sum_{(j,o)} |start_{new}(j,o) - start_{base}(j,o)|. To achieve this, never start any operation earlier than the baseline. When repairing operations in precedence-aware order, place each operation at the earliest feasible time. Anchor is calculated by anchor(j,o) = \max(start_{base}(j,o), end_{new}(j,o-1)), end_{new}(j,o-1) is end time of the previous operation of the same job at the new schedule. If start > anchor, then start-1 must be infeasible. You guarantee this by scanning integer time forward by +1 from anchor. Jumping to “next gap” without checking every integer may break minimality. If the given baseline is invalid, replace the machine with a feasible one.

Here is the pipeline. For each operation, first find the earliest time to start. It cannot start earlier than the baseline, and it cannot start before the previous operation of the same job finishes. Then list only the machines that are allowed for this operation, and use the processing time that belongs to each machine. For each candidate machine, find the allowed earliest time and pick the first start time that does not overlap with other work on that machine and does not fall into any downtime window. Choose the option that makes the smallest changes overall. Prefer not changing machines and keeping start-time shifts small, and make sure you stay within the policy budgets. After selecting a start time, immediately record this operation on the machine timeline in the same precedence-aware order, so the result matches the evaluator’s step-by-step simulation.

Here are reference codes.

# sorted Downtime windows
downtime[m] = sorted([(start,end), ...])
def overlap(s,e,a,b):
    return s \x3C b and a \x3C e  
# Precedence-aware repair order
def precedence_aware_order(base_list):
    base_map = {(r["job"], r["op"]): r for r in base_list}
    base_index = {(r["job"], r["op"]): i for i, r in enumerate(base_list)}
    keys = list(base_map.keys())
    keys.sort(key=lambda k: (k[1], base_map[k]["start"], base_index[k]))
    return keys
def earliest_feasible_time(m, anchor, dur, machine_intervals, downtime, safety=200000):
    t = int(anchor)
    for _ in range(safety):
        if not has_conflict(m, t, t+dur, machine_intervals, downtime):
            return t
        t += 1
    return t
def has_conflict(m, st, en, machine_intervals, downtime):
    for a,b in machine_intervals.get(m, []):
        if overlap(st,en,a,b):
            return True
    for a,b in downtime.get(m, []):
        if overlap(st,en,a,b):
            return True
    return False
# Baseline machine may be illegal
base_m = base_map[(j,o)]["machine"]
if base_m not in allowed[(j,o)]:
    # baseline is invalid; pick a legal default (min duration is a good heuristic)
    base_m = min(allowed[(j,o)], key=lambda m: allowed[(j,o)][m])
base_d = allowed[(j,o)][base_m]
#Use a lexicographic score that matches your priorities
machine_change = int(mm != base_m_orig)  
start_shift    = abs(st - base_start)
score = (machine_change, start_shift, st, mm)
#Then pick the smallest score, but respect remaining machine-change budget.
#A naive “always keep baseline machine” can cause large start shifts. This often reduces `Shift_L1` enough to pass tight budgets without exploding machine changes. Use a simple trigger to consider alternates *only when it helps*:

THRESH = 6  # tune; small instances often 3~10 works
# First try baseline machine
cand = best_candidate_restricted_to([base_m])

# If shift is large and we still can change machines, search alternates
if (cand.start - base_start) >= THRESH and mc_used \x3C max_mc:
    cand2 = best_candidate_over_all_allowed_machines()
    if cand2.start \x3C cand.start:   # or cand2.shift \x3C cand.shift
        cand = cand2
Usage Guidance
This skill appears coherent and low-risk: it only describes an algorithm for repairing schedules and asks for no credentials or installs. Before using it, make sure you (or the caller) provide the required inputs in the expected formats (baseline list, allowed machine map, downtime windows, policy budgets). Be aware the naive integer-by-integer scan (earliest_feasible_time with a large safety bound) may be very slow for long horizons—consider implementing an efficient gap-search (interval skipping) or lowering the safety bound. Also validate inputs (durations, allowed machines, baseline legality) and test on small instances to confirm the behavior of tie‑breaking (lexicographic score and THRESH) matches your policy constraints.
Capability Analysis
Type: OpenClaw Skill Name: manufacturing-fjsp-optimization-fjsp-baseline-repair-with-downtime-and-policy Version: 0.1.0 The skill bundle contains instructions and Python snippets for optimizing Flexible Job Shop Scheduling (FJSP) schedules. The logic focuses on repairing schedules to meet downtime and precedence constraints while minimizing machine changes and start-time shifts (SKILL.md). There are no indicators of data exfiltration, malicious execution, or prompt injection; the code is entirely focused on the stated manufacturing optimization task.
Capability Assessment
Purpose & Capability
The name/description describe repairing fjsp baselines; the SKILL.md contains step‑by‑step scheduling logic and pseudocode that match that purpose. There are no unrelated dependencies, environment variables, or install steps requested.
Instruction Scope
Instructions are narrowly about computing earliest feasible start times, honoring precedence, downtime windows, and policy budgets. They do not instruct reading unrelated files, environment variables, or contacting external endpoints. The SKILL.md is algorithmic and presumes the caller supplies baseline lists, allowed machines, downtime and machine timelines.
Install Mechanism
No install spec or code files are present (instruction-only). Nothing will be downloaded or written to disk by the skill itself.
Credentials
The skill requires no environment variables, credentials, or config paths; no excessive secrets are requested.
Persistence & Privilege
always is false and the skill does not request persistent presence or attempt to modify other skills or system settings.
How to Use
  1. Make sure OpenClaw is installed (local or Docker)
  2. Run the install command in chat: /install manufacturing-fjsp-optimization-fjsp-baseline-repair-with-downtime-and-policy
  3. After installation, invoke the skill by name or use /manufacturing-fjsp-optimization-fjsp-baseline-repair-with-downtime-and-policy
  4. Provide required inputs per the skill's parameter spec and get structured output
Version History
v0.1.0
Bulk publish from all-task-skills-dedup
Metadata
Slug manufacturing-fjsp-optimization-fjsp-baseline-repair-with-downtime-and-policy
Version 0.1.0
License MIT-0
All-time Installs 0
Active Installs 0
Total Versions 1
Frequently Asked Questions

What is fjsp-baseline-repair-with-downtime-and-policy?

This skill should be considered when you need to repair an infeasible or non-optimal flexible job scheduling planning schedule into a downtime-feasible, prec... It is an AI Agent Skill for Claude Code / OpenClaw, with 71 downloads so far.

How do I install fjsp-baseline-repair-with-downtime-and-policy?

Run "/install manufacturing-fjsp-optimization-fjsp-baseline-repair-with-downtime-and-policy" in the OpenClaw or Claude Code chat to install it in one step — no extra setup required.

Is fjsp-baseline-repair-with-downtime-and-policy free?

Yes, fjsp-baseline-repair-with-downtime-and-policy is completely free, licensed under MIT-0. You can download, install and use it at no cost.

Which platforms does fjsp-baseline-repair-with-downtime-and-policy support?

fjsp-baseline-repair-with-downtime-and-policy is cross-platform and runs anywhere OpenClaw / Claude Code is available (cross-platform).

Who created fjsp-baseline-repair-with-downtime-and-policy?

It is built and maintained by lnj22 (@lnj22); the current version is v0.1.0.

💬 Comments